APM- PFQ EXAM LATEST 2024 ACTUAL EXAM TEST BANK 420 QUESTIONS AND CORRECT DETAILED ANSWERS (VERIFIED ANSWERS) |ALREADY GRADED A+

APM- PFQ EXAM LATEST 2024 ACTUAL EXAM

TEST BANK 420 QUESTIONS AND CORRECT

DETAILED ANSWERS (VERIFIED ANSWERS)

|ALREADY GRADED A+

Which one of the following is least likely to be a success criteria?

a. A target for the project to receive zero change requests.

b. The date by which the project is to be completed.

c. Delivery of products that meet required specifications.

d. The awarding of bonuses to senior management. - ANSWER- D

Which one of the following is a valid project Key Performance Indicator

(KPI)?

a. Staff appraisals.

b. Management buy in.

c. Milestone achievement.

d. Master schedule. - ANSWER- C

Which one of the following statements is true?

a. The business case is owned by the sponsor and is created during the

concept phase of the project life cycle.

b. The business case is owned by the project manager and is created

during the concept phase of the project life cycle.


c. The business case is owned by the sponsor and is created during

definition phase of the project life cycle.

d. The business case is owned by the project manager and is created

during the definition phase of the project life cycle. - ANSWER- A

Who owns the Project Management Plan (PMP)?

a. The project team.

b. The chief executive.

c. The project manager.

d. The project support office - ANSWER- 11

Which one of the following best describes users?

a. Providers of both strategic and tactical direction to the project.

b. Those intended to receive benefits or operate outputs.

c. Facilitators of an appropriate issue resolution procedure.

d. Those providing full-time commitment to the project. - ANSWER- B

Which statement best describes a responsibility of the project manager:

a. to be the sole source of expertise for estimating techniques on cost and

time.

b. to deliver the project objectives to enable benefits to be realised.

c. to take ultimate accountability for the delivery of the business

benefits.

d. to delegate all accountability for managing time, cost and quality to

team leaders - ANSWER- B


A project is typically defined in terms of scope, time, cost and which

other parameter?

a. Benefits.

b. Quality.

c. Tolerance.

d. Controls. - ANSWER- B

Which one of the following statements is true?

a. Business-as-usual activities cannot be improved.

b. Business-as-usual activities are more difficult to manage than

projects.

c. Projects are transient endeavours that bring about change to businessas-usual.

d. A project is always the starting point for operation refinement. -

ANSWER- C

What is defined as "the ability to influence and align others towards a

common purpose"?

a. Teamwork.

b. Motivation.

c. Management.

d. Leadership - ANSWER- D

Which one is a true statement relating to project communications?


a. A project sponsor is responsible for all communication methods and

media.

b. Different stakeholders typically have different communication needs.

c. It is best to have a standard set of project reports used for every

project.

d. Email is the only way to communicate with large numbers of people. -

ANSWER- B

In project management, the term quality is best defined as:

a. inspection, testing and measurement.

b. reviews and audits.

c. fitness for purpose of deliverables.

d. professionally-bound project reports. - ANSWER- C

The main outcome of risk identification, in a risk management process,

is to:

a. identify and determine the relative importance of the project risks.

b. identify and describe all risks that might occur on the project.

c. identify and determine the responses to the project risks.

d. identify and describe risks that have occurred on previous projects -

ANSWER- B

Which one of the following is not considered in resource management?

a. Identifying resources.

b. Influencing resources.


No comments found.
Login to post a comment
This item has not received any review yet.
Login to review this item
No Questions / Answers added yet.
Price $31.00
Add To Cart

Buy Now
Category Exams and Certifications
Comments 0
Rating
Sales 0

Buy Our Plan

We have

The latest updated Study Material Bundle with 100% Satisfaction guarantee

Visit Now
{{ userMessage }}
Processing