Question 1
4 out of 4 points
Most of the scheduling methods available today require the project
manager to classify the project as either _______ constrained or ______
constrained.
Selected
Answer:
e.
Time,
resource
Correct
Answer:
e.
Time,
resource
Question 2
4 out of 4 points
In reviewing the status of her project with top management, Shirley was
told that there are only two programmers that she can use for her project.
Her project is classified as __________ constrained.
Selected
Answer:
e.
Resour
ce
Correct
Answer:
e.
Resour
ce
Question 3
4 out of 4 points
Gene is trying to order the concrete needed to continue his project.
However, the supplier will not be able to deliver it until next week. This is
an example of what kind of resource constraint?
Selected
Answer:
e.
Materi
als
Correct
Answer:
e.
Materi
als
Question 4
4 out of 4 points
Resources are adequate, but demand varies widely over the life of the
project. Delaying noncritical activities to lower peak demand on resources
is known as resource
Selected
Answer:
d.
Smoothi
ng.
This study source was downloaded by 100000844708667 from CourseHero.com on 11-23-2022 00:05:34 GMT -06:00
https://www.coursehero.com/file/16134781/BUS-375-Exam-2-Part-A-100-points/
BUS 375 EXAM 2 PART A QUESTIONS WITH
COMPLETE SOLUTIONS 100% POINTS
Correct
Answer:
d.
Smoothi
ng.
Question 5
4 out of 4 points
All resource leveling techniques involve
Selected
Answer:
a.
Delaying noncritical
activities.
Correct
Answer:
a.
Delaying noncritical
activities.
Question 6
4 out of 4 points
When a company will reduce the number of projects they have to manage
internally to only core projects and send noncritical projects to contractors
and consulting firms this is called
Selected
Answer:
a.
Outsourci
ng.
Correct
Answer:
a.
Outsourci
ng.
Question 7
4 out of 4 points
Tony has realized that two activities in his project cannot be done at the
same time because not enough resources are available. Activity 3 is
critical and has a duration of 5 days. Activity 4 has 2 days of slack and a
duration of 2 days. How will he decide which activity should be scheduled
first?
Selected
Answer:
b.
The activity with the
least slack
Correct
Answer:
b.
The activity with the
least slack
Question 8
4 out of 4 points
Which of the following is NOT a potential consequence of failing to identify
limited resources before project implementation?