1. The method of computation of Contractor's overhead and profits for Change Order prices, where both additions and deletions are involved, is found in the: a) Agreement. b) Conditions of the Contract. c) Division 01. d) Instructions to Bidders. b) Conditions of the Contract. 2. General Requirements are part of: a) Supplementary Conditions. b) Bidding Requirements. c) Specifications. d) Summary of Work. c) Specifications. 3. The three essential considerations in the evaluation of a product are: a) Requirements, Criteria, and Tests. b) Costs, Maintenance, and Installation. c) Life Cycle Cost, Installation Cost, and Maintenance Cost. d) Case studies, Failures, and Problems. a) Requirements, Criteria, and Tests. 4. Whose responsibility is it to furnish the Shop Drawings? a) The Architect/Engineer b) The Contractor c) The Owner d) The Subcontractor b) The Contractor 5. The division of the Work among multiple prime Contracts is described in: a) Instructions to Bidders. b) Supplementary Conditions. c) Division 01. d) Special Conditions. c) Division 01. 6. During the Project Conception Stage, the A/E may be retained to: a) Develop outline specifications b) Describe the character of the mechanical system c) Prepare renderings d) Assist in financial feasibility studies d) Assist in financial feasibility studies 7. What is the main purpose of MasterFormat? a) for scheduling, value management, recording of design data and managing costs. b) used during the planning stage of a project. c) to organize the Project Manual, reference keynotes and detailed cost estimates. d) when there is a standardized need for information to appear upon each page of a project manual. c) to organize the Project Manual, reference keynotes and detailed cost estimates. 8. The person who becomes secondarily liable for another's debt or performance is called the: a) Guarantee b) Warrantor c) Guarantor d) Warrantee c) Guarantor 9. Integrated projects are distinguished by all of the following characteristics except: a) Development of virtual project model through input from a collaborative team b) Trust-based collaboration between project team members c) Maximized efficiency through design, fabrication, and construction d) "Just as needed" team involvement to reduce owner's pre-construction expenses d) "Just as needed" team involvement to reduce owner's pre-construction expenses 10. Outline Specifications are written for a) only Divisions 02-14 where actual products are discussed b) Divisions 01-49 c) only Divisions 01-14 (excluding mechanical and electrical) d) the exclusive use of the A/E b) Divisions 01-49 11. An example of a MasterFormat Level 3 specification Section is: a) 05 00 00 Metals. b) 05 20 00 Metal Joists. c) 05 21 00 Steel Joist Framing. d) 05 21 19 Open Web Steel Joist Framing. d) 05 21 19 Open Web Steel Joist Framing. 12. What activities take place in the Project Conception Stage? a) The engineers develop the mechanical and electrical systems. b) The site is selected and the demolition is done. c) Feasibility studies and budget is set. d) The program is evaluated and the engineers are selected. c) Feasibility studies and budget is set. 13. The document recommended to organize preliminary construction information into a standard order on the basis of systems and assemblies is: a) MasterFormat b) Uniformat c) Outline Specifications d) Project Manual b) Uniformat 14. All design and construction drawings can be classified as one of two types of views: a) Numeric and graphic. b) Vertical and horizontal. c) Scaled and nonscaled. d) Exterior and interior. c) Scaled and nonscaled. 

No comments found.
Login to post a comment
This item has not received any review yet.
Login to review this item
No Questions / Answers added yet.
Price $13.00
Add To Cart

Buy Now
Category exam bundles
Comments 0
Rating
Sales 0

Buy Our Plan

We have

The latest updated Study Material Bundle with 100% Satisfaction guarantee

Visit Now
{{ userMessage }}
Processing