You are the contracting officer for a firm-fixed price supply
contract valued at $195,400. Which one of the following
statements about contract closeout is correct? - CORRECT
ANSWER The contract is considered closed once you receive
evidence of receipt of property and final payment.
Which of the following statements is true regarding the policies for
the use of simplified acquisition procedures (SAP)? - CORRECT
ANSWER Purchases shall be made in the simplified manner
that is most suitable to the circumstances of the acquisition.
You have just been informed that a purchase order you recently
awarded for commercial supplies is no longer needed and must
be cancelled. The order was not accepted in writing by the
contractor. Which one of the following statements is true? -
CORRECT ANSWER The purchase order is considered
cancelled if the contractor accepts the Government's written
cancellation and does not claim costs were incurred.
Which one of the following statements about the evaluation of
quotations or offers using SAP is true? - CORRECT ANSWER
Quotations or offers must be evaluated using the basis stated in
the solicitation.
You just made an award for services in the amount of $235,200
based on price and past performance. One of the unsuccessful
vendors has requested information on the award decision. Which
one of the following describes the action you must take? -
CORRECT ANSWER You must provide a brief explanation of
the basis for the award decision.
You have a one-time requirement for a purchase of
noncommercial supplies with an estimated value of $235,000.
The supplies are not immediately. Which one of the following
simplified acquisition methods would be the most appropriate to
use? - CORRECT ANSWER Purchase Order
You have a requirement for a new contract for grounds
maintenance at your military installation. The Base Commander
has expressed the need for clearly stated performance objectives,
as the current contractor performaing the services is not meeting
the Commander's expectations. Consistent with order of
precedence for requirements documents, which one of the
following documents would be included in the new contract? -
CORRECT ANSWER A Performance Work Statement (PWS)
Which one of the following is NOT a mandatory Government
source for satisfying a supply requirement? - CORRECT
ANSWER Commercial sources
You have a requirement for a purchase with an estimated value of
$8,700. Which one of the following describes the competition
requirement for this acquisition? - CORRECT ANSWER There
is no requirement for competition if the price is considered
reasonable.
Which one of the following is NOT one of the first steps taken
when quotations are received in response to a solicitation using
SAP? - CORRECT ANSWER Ranking the quotations by
technical acceptability
You have a requirement for repair parts to support routine
maintenance services at the shop on your base.