Here is your test result.The dots represent the choices you have made.
The highlighted questions are the questions you have missed.
Remediation Accessed shows whether you accessed those links.'N' represents links not
visited and 'Y' represents visited links.
1.) In determining the correct appropriation for funding the development of a
product improvement, the first/primary consideration is:
Will it increase the performance capability?
Is the system still in production?
Will the operator install the modification?
Will the same contractor produce the item?
2.) Which of the following are duties of a Program Integrator (Select all that
apply)?
Administering day to day contractual activities after contract award
Has a direct line of communication with the Procuring Contracting Officer
"Eyes and ears" of the Program Manager
Provide data to the Program Manager
Lead and direct the program support team
3.) The Army has an urgent requirement for trucks that can operate under arctic
conditions. The Contracting Officer on the current contract for trucks tells the
contractor to install special snow tires on a shipment of trucks. The Contracting
Officer does not have enough time to negotiate the price up front, but she limits
the Government's risk by putting a not-to-exceed price on the work. This is an
example of what kind of modification?
A supplemental agreement
This study source was downloaded by 100000853564414 from CourseHero.com on 09-28-2022 18:28:21 GMT -05:00
https://www.coursehero.com/file/18385071/Module-5-Exam/
A constructive change
A modification that is definitized
A change order that is undefinitized
4.) Any Government employee can make changes to a contract as long as the
Government will benefit from the changes.
True
False
5.) Variability reduction is one way of controlling manufacturing costs.
True
False
6.) Lean manufacturing tends to increase manufacturing costs and delay
schedules in the manufacturing process.
True
False
7.) Choose the ideal cost of quality breakdown from the following options.
Prevention 15%, Appraisal 35%, Failure 50%
Prevention 5%, Appraisal 45%, Failure 50%
Prevention 50%, Appraisal 35%, Failure 15%
Prevention 25%, Appraisal 50%, Failure 25%
This study source was downloaded by 100000853564414 from CourseHero.com on 09-28-2022 18:28:21 GMT -05:00
https://www.coursehero.com/file/18385071/Module-5-Exam/
8.) Estimates based on learning curve theory may NOT apply if ________.
Units of production are homogeneous
The factory workforce remains stable
The production process continues for 18 months without a break
The design of the product keeps changing
9.) Manpower, measurement, methods, machinery, and materials are collectively
referred to as the ___________________.
5Ms of Engineering
5Ms of Industry
Elements of Production
5Ms of Manufacturing
10.) Which process is recommended for those products with the highest volume
and the highest standardization on the product continuum?
Assembly line
Continuous flow
Batch
Jumbled flow
11.) Which of the following results in a flatter learning curve?
Low rate of workforce turnover