NERC EXAM, TEST, PRACTICE EXAM AND STUDY GUIDE LATEST ACTUAL EXAM 600 QUESTIONS AND CORRECT DETAILED ANSWERS WITH RATIONALES (VERIFIED ANSWERS) |ALREADY GRADED A+

NERC EXAM, TEST, PRACTICE EXAM AND STUDY

GUIDE LATEST 2023-2024 ACTUAL EXAM 600

QUESTIONS AND CORRECT DETAILED ANSWERS

WITH RATIONALES (VERIFIED ANSWERS)

|ALREADY GRADED A+

NERC EXAM

1. If a 500 kV transmission line with a surge impedance loading of 800 MW is

currently loaded at 1400 MW, which of the following events would most likely

occur?

a. Generator MVAR output would increase

b. All system capacitors would trip off-line

c. Generator MVAR output would decrease

d. All automatic reactors would connect to the system - ANSWER- a. Generator

MVAR output would increase

2. When system conditions are such that emergency procedures are expected to be

implemented, which of the following actions should be considered first?

a. Shed firm load

b. Implement Active Load Management

c. Return outaged equipment to service

d. Request a voltage reduction - ANSWER- c. Return outaged equipment to

service


3. If your transmission path is rated for 1200 MW and 1000 MW are scheduled on

it, but due to parallel flows the actual flow is 1300 MW, what action should you

take?

a. Request that a phase shifting transformer be installed

b. Reduce interchange transactions impacting the path

c. Request all parallel flow to PSEs to increase schedules

d. Reduce all commercial customer load - ANSWER- b. Reduce interchange

transactions impacting the path

4. If your system is MVAR deficient, what action could be implemented to prevent

voltage collapse?

a. Raise system frequency above 60.5 Hz

b. Shed firm load in the deficient area

c. Separate from the Interconnection

d. Lower transmission voltages - ANSWER- b. Shed firm load in the deficient area

5. Which of the following actions can a system operator take in order to maintain

stability on the system?

a. Request generators to absorb maximum MVAR

b. Place all operating limits on dynamic calculation

c. Raise system voltages as high as possible, but within their operating parameters

d. Reduce voltages on the transmission system - ANSWER- c. Raise system

voltages as high as possible, but within their operating parameters


6. Which of the following actions should you take if an outage on a neighboring

system has caused a violation on your system?

a. Open all tie-lines to your neighbor

b. Ask the Reliability Coordinator for assistance

c. Shed load to mitigate the violation

d. Wait for the neighboring system to contact you - ANSWER- b. Ask the

Reliability Coordinator for assistance

7. If a SOL or IROL violation occurs due to transfers across the system and it is

determined that parallel flows are contributing to the violation, what should the

system operator do?

a. Place all system capacitors in service

b. Reduce system load

c. Inform the Reliability Coordinator

d. Dump firm load - ANSWER- c. Inform the Reliability Coordinator

8. While performing a pre-outage study, you identify that the transmission outage

will cause a thermal violation on a parallel path, which of the following actions

would be the first one you would implement?

a. Shed load to mitigate the concern

b. Allow the outage to occur and see what happens

c. Reschedule the outage if possible

d. Allow the outage to take place as long as no load is lost - ANSWER- c.

Reschedule the outage if possible


9. Which of the following actions should the system operator implement first if

transmission line limits exceed the facilities emergency limits based on a

contingency that has not yet occurred, but their protocols are to respond on a precontingency basis?

a. Reduce voltages in the area of the violation

b. Remove the facility from service

c. Curtail any interchange transactions that are curtailable

d. Only implement actions if the contingency occurs - ANSWER- c. Curtail any

interchange transactions that are curtailable

10. If a Reliability Coordinator had to implement any type of line loading relief

procedures, which of the following entities would they be coordinated with? Pick

two.

a. Purchasing Selling Entities

b. Balancing Authorities

c. Transmission Operators

d. Load Serving Entities - ANSWER- b. Balancing Authorities

c. Transmission Operators

11. If a generator is lost in a neighboring Balancing Area, what would the impact

be on the BAs transmission tie lines?

a. Nothing

b. A net increase of MW would come into your BAs system

c. A net increase of MW would go out of your BAs system


No comments found.
Login to post a comment
This item has not received any review yet.
Login to review this item
No Questions / Answers added yet.
Price $41.00
Add To Cart

Buy Now
Category Exams and Certifications
Comments 0
Rating
Sales 0

Buy Our Plan

We have

The latest updated Study Material Bundle with 100% Satisfaction guarantee

Visit Now
{{ userMessage }}
Processing