Which pre-project actions reduce risk and increase the
probability of project success? The correct answer is: Preselect contractors
If an organization has narrowed the list of contractors submitting
proposals but is still having trouble deciding between them,
what could help? The correct answer is: Bidder presentations
Which statement is true of the Execute, Monitor and Control
phases of the project model? The correct answer is: These
phases are often concurrently or iteratively performed.
When project managers determine the level of data to collect for
monitoring and controlling project work, what do they not need
to verify?The correct answer is: Project work delays due to data
collection are scheduled.
What do project managers submit when they suggest revising
the project management plan to make it feasible given the
current situation? The correct answer is: change order.
What is developed to review a final deliverable from an entire
system perspective? The correct answer is: Checklist
reviews
Which statement is true about the documentation for project
closure? The correct answer is: Documentation may include
operations and maintenance manuals.
A project manager wants to minimize risk and provide some
independent checks and balances on contractor work. Which
contract model should the organization use? Construction
management Your answer is correct.
Construction management is the best choice because it uses
an independent consultant to supervise separate contracts
with design firms and construction firms, which allows for
some independent review. (Reference: 3-2-10)
According to the critical path method (CPM) of scheduling,
what is the critical path for any project?the longest set of
sequential tasks in the project. Your answer is correct.
The critical path is the longest set of sequential tasks in a
project and indicates the shortest possible project duration.
The critical path is determined using forward pass
scheduling followed by backward pass
scheduling.(Reference: 3-2-3)
Why does a budget need to be closely integrated with the project
schedule?costs are allocated to the period in which they occur.
Your answer is correct.
Development of the budget requires close integration with
the project schedule because costs are allocated to the period
in which the costs are incurred. Similarly, budget constraints
can require changes to the project schedule such as
completing a task more quickly to minimize financing costs.
Budgets are produced after schedules. Estimates for costs
are made during planning rather than waiting until
later.(Reference: 3-2-5)
Which scheduling methods are for activities NOT concurrently
performed? Traditional waterfall model scheduling Your
answer is correct.