You have a requirement for repair parts to support routine maintenance services at the
shop on your base. The parts were
developed using Government funds and are not offered to the general public. The
estimated dollar value of the acquisition is
$275,000.
Which one of the following statements is true? - Answer The use of simplified
acquisition procedures is prohibited.
You are the contracting officer for a firm-fixed-price supply contract valued at $195,400.
Which one of the following
statements about contract closeout is correct? - Answer The contract is considered
closed once you receive evidence of receipt of property and final payment.
You are the contracting officer for a noncommercial supply contract valued at $155,600.
Which one of the following actions
would be executed using a bilateral modification?
(There is another question almost Identical to this one) - Answer Making a negotiated
equitable adjustment
You have a requirement for a new contract for janitorial services at your military
installation. The Base Commander has
expressed the need for clearly stated performance objectives, as the current contractor
performing the services is not
meeting the Commander's expectations.
Consistent with the order of precedence for requirements documents, which one of the
following documents would be
included in the new contract? - Answer A Performance Work Statement (PWS)
Which one of the following mandatory Government sources is the first priority for
satisfying a requirement for supplies? - Answer Inventories of the requiring agency