All of the following are true regarding UST systems installed after July 1, 2003 and before July 1, 2004, EXCEPT?
a. Portions of vent lines, vapor recovery lines, and fill pipes that are beneath the surface of the ground are "pipe" and therefore part of the underground storage tank system.
b. Pipe does not include vent lines, vapor recovery lines, and fill pipes that are designed to prevent, and do not hold, standing fluid in the pipes or lines.
c. Primary containment shall be product tight and compatible with stored product.
d. Secondary containment shall be product tight and constructed to prevent structural weakening as a result of contact with any hazardous substances released from the primary containment.
b. Pipe does not include vent lines, vapor recovery lines, and fill pipes that are designed to prevent, and do not hold, standing fluid in the pipes or lines.
H&SC 25290.2
Which of the following operational requirements must an operator comply with for an automatic line leak detector?
a. Test the foot valve annually.
b. Exercise the "automatic reset" monthly.
c. Check the interstitial space weekly for liquid.
d. Test the automatic line leak detector's operation certified every 12 months.
d. Test the automatic line leak detector's operation certified every 12 months.
CCR; 2638
The regulations to enforce compliance of underground storage tank systems in the state are found in?
a.) Code of Federal Regulations, 40 CFR Part 281
b.) California Code of Regulations, Title 23, Chapter 16
c.) Code of Federal Regulations, 40 CFR Part 280
d.) California Code of Regulations, Title 23, Chapter 17
b.) California Code of Regulations; Title 23, Chapter 16
By definition an "underground storage tank system" includes
a.) The tank, all connected piping and dispensers
b.) The tank, all connected piping, ancillary equipment and containment system
c.) Only the tank
d.) Only tanks totally beneath the surface of the ground
b.) The tank, all connected piping, ancillary equipment and containment system
(H&SC, Sec 25281(z))
Under-dispenser containment was required for all UST systems by ___________.
a.) December 31, 2003
b.) July 1, 1987
c.) January 1, 1984
d.) January 1, 2000
a.) December 31, 2003
CCR Title 23, Sec 2636(g)(C)
According to California Law, UST systems installed after July 1, 2003, require a one-time ELD test to ensure that the tank is product tight...
a.) If the tank is located within one (1) mile of a public drinking water well
b.) If the tank is located within 1000 feet of a public drinking water well
c.) Unless the tank is equipped with secondary containment
d.) In all cases
For ALL tanks before use (H&SC 25290.2 (I))
d.) In all cases