1. What is the primary benefit of conducting a stakeholder analysis in the initial stages of a project? - A) To determine the project schedule - B) To identify potential risks - C) To assess the communication needs of stakeholders - D) To allocate project resources efficiently Answer: C) To assess the communication needs of stakeholders Rationale: Understanding the communication requirements of stakeholders early helps in planning effective engagement strategies, ensuring their needs are met, and aligning their expectations with project goals. 2. In Agile project management, what does the term "timeboxing" refer to? - A) Assigning specific time slots for meetings - B) Limiting the time spent on a particular task or activity - C) Extending project deadlines - D) Scheduling project milestones


No comments found.
Login to post a comment
This item has not received any review yet.
Login to review this item
No Questions / Answers added yet.
Price $17.00
Add To Cart

Buy Now
Category WGU EXAM
Comments 0
Rating
Sales 0

Buy Our Plan

We have

The latest updated Study Material Bundle with 100% Satisfaction guarantee

Visit Now
{{ userMessage }}
Processing